For those that might fly into Flint. Please share with operators that might go there.
BIAA Taxiway C (West) Rehabilitation Construction Project. June 18, 2018 thru October 14, 2018.
Portions of Taxiway C West of Runway 18/36 will be closed.
When landing Runway 27, plan to make a 180 on the runway and back taxi on the runway due to closures on the C, C5, C4 connectors.
FBO Apron limited to Group II aircraft (79’ wingspan or less).
Aircraft with more than a 79’ wingspan that would normally park on FBO Apron, plan to park on Cargo Apron.
Main entrances to FBO Apron and Cargo Apron will be closed or modified during this project. Temporary taxilanes or narrowed entrances will be in effect at times.
Runway 9/27 (up to 4 weeks) and Runway 18/36 (up to 7 days) will be closed during this project.
NAVAIDS serving runways that are closed during this project will be de-energized until the runway reopens.
Runway lighting/taxiway lighting on any closed surface area will be de-energized until reopened.
Lighted X’s will be placed on closed runways.
Low barricades will be placed on closed portions of taxiways.
Check NOTAMs and ATIS constantly.
Contact: Patrick M. Ryan FAASTeam Ops Program Manager
EMI FSDO (734) 487-7455 patrick.m.ryan@faa.gov