KBDL runway construction project will start on 4/21 and end on 11/21/25.  There will be multiple phases as indicated below:

  • Phase 1: 4/21-5/1/25.  RY 15/33 closed but available for taxi.  Taxiway S/D intersection closed. Runway 6/24 remains open. 
  • Phase 2-6: 5/1-11/21/25. RY 6/24 closed.  Portions of taxiway C and E will close based on the specific phase. 
  • Phase 4: 8/9-8/11, 8/16-8/18, 8/23-8/25, 9/6-9/8, 9/13-9/15, 10/4-10/6, 10/11-10/13, 10/18-10/20, 10/25-10/27.  Runways 15/33 and 6/24 closed for construction at the intersection nightly 0000L-0530L.  There are some rain dates, but these are the planned closures limited to the 5.5 hour block.  These are hard closures with no PPR and no delays.